The NEPA: Environmental Impact Statements, Compliance, and an Impending Threat to Environmental Regulation

On March 25, 2020, a judge for the United States District Court in the District of Columbia held that the Army Corp of Engineers (hereinafter the Corp) failed to comply with the standards of the National Environmental Policy Act (hereinafter “the Act”) by failing to prepare an Environmental Impact Statement (EIS) before deciding to approve federal permits for construction of a portion of the Dakota Access Pipeline which ran under the Mississippi River.  The ruling came four years after the Standing Rock Sioux Tribe brought the original action in 2016.  The Act is meant to ensure the public that agencies have considered the environmental consequences of a potential project before going forward with it, and so requires agencies to consider any and every significant environmental impact that could result from the project through completion of an Environmental Assessment, and, in some cases, an Environmental Impact Statement (EIS).